Correct Answer: A
Explanation
= The project manager should meet with the stakeholder to understand what is causing the delays in approving the project deliverables. This is the best way to address the stakeholder's concerns, expectations, and needs, and to build trust and rapport with them. The project manager should also communicate the impact of the delays on the project progress and seek the stakeholder's feedback and support. The other options are not the best actions to take in this situation, as they do not involve direct communication with the stakeholder or attempt to resolve the underlying issue. References: = A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 3: Stakeholder Performance, Section 3.2: Engage Stakeholders, Page 77-78.