Valid CORe Dumps shared by ExamDiscuss.com for Helping Passing CORe Exam! ExamDiscuss.com now offer the newest CORe exam dumps, the ExamDiscuss.com CORe exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CORe dumps with Test Engine here:
UVW, Inc. issues a Request for Quotation (RFQ) for urgently-needed safety equipment. The equipment must be installed immediately in order to keep the firm in compliance with safety regulations. UVW is contacted by a small, minority-owned company which asks for two more weeks to submit its quotation, as its technical expert is out sick. In this situation, which of the following is the MOST appropriate course of action for UVW to take?