While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report: Approved Work Package Cost Estimates: US$9,500 Contingency reserves: $500 Management reserves: 10% of contingency reserves Percent complete of the project: 50% Planned percent of the project: 40% Actual costs of the project: US$4,500 What is accurate about the project status?
Correct Answer: B
Step-by-step analysis: 1. Calculate Budget at Completion (BAC) Work package estimates = $9,500 Contingency reserve = $500 BAC = 9,500 + 500 = $10,000 (Management reserve is not included in EVA baseline) 2. Calculate Planned Value (PV) Planned % = 40% PV = 40% × 10,000 = $4,000 3. Calculate Earned Value (EV) Actual % complete = 50% EV = 50% × 10,000 = $5,000 4. Actual Cost (AC) AC = $4,500 Cost Performance: CPI = EV / AC = 5000 / 4500 ≈ 1.11 This means the project is about 11% under budget (≈10% for answer purposes) Schedule insight (for completeness): EV (5000) vs PV (4000) -> ahead of schedule That's 25% more work completed than planned, but the question focuses on cost