Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
In a software project using an agile approach, there have recently been work overruns. After assessing the situation, the project manager concluded that the overruns are occurring because of insufficiently refined product backlog items. What should the project manager do to correct this issue?
Correct Answer: B
A definition of ready (DoR) is a set of criteria or conditions that a product backlog item (PBI) must meet to be considered ready to be pulled into the sprint backlog. A DoR ensures that the PBIs are clear, feasible, valuable, testable, and independent. By creating a DoR for the backlog items, the project manager can avoid work overruns and ensure that the team can effectively tackle the tasks in the sprint.