A project manager is leading a complex project spanning multiple departments. During a recent status meeting, few team members and stakeholders expressed concerns that they were missing some of the important project updates or that they were informed too late. What should the project manager do?
Correct Answer: D
The project manager should review the communications management plan to identify gaps in stakeholder information needs, timing, channels, frequency, and responsibilities. The plan can then be updated so critical project information reaches the appropriate people promptly.