A stakeholder requests a significant change during late project execution. The project manager analyzes impacts on scope, schedule, and cost. Which is the recommended PMI process?
Correct Answer: B
PMI emphasizes formal change control. Every change must be documented, analyzed, and approved. Informal approval or rejection without analysis risks project integrity and misalignment with objectives.