It is taking several additional iterations for a project team to complete planned backlog items. The project manager is noticing that some of the features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?
Correct Answer: B
The team should reinforce a shared understanding of the definition of done so backlog items meet all required quality and completion conditions within the iteration. Clear adherence prevents incomplete features from being repeatedly returned to the backlog.