A project learn member identified a defect in the initial solution design for a project. The stakeholders are not sure whether to deploy the system or not. What should the project manager do?
Correct Answer: B
According to the PMBOK Guide, one of the tools and techniques for performing integrated change control is risk analysis. This involves assessing the potential impact of a change request or a defect on the project objectives, such as scope, schedule, cost, and quality. By performing risk analysis, the project manager can evaluate the pros and cons of deploying the system with the defect, and determine the best course of action.