Valid PMP Dumps shared by ExamDiscuss.com for Helping Passing PMP Exam! ExamDiscuss.com now offer the newest PMP exam dumps, the ExamDiscuss.com PMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMP dumps with Test Engine here:
A migration deployment is scheduled in 2 weeks, and a stakeholder is requesting a code change. The code change requires two developers, and testing the code will require two quality engineers. Further, the change will push the planned deployment date back by 1 week and delay the start of the next migration. What action should the project manager take?
Correct Answer: A
The project manager should first assess the request's business priority and its effects on resources, testing, deployment, downstream migrations, cost, and risk. Based on that analysis, the proposed one-week schedule change should follow the appropriate approval process before the deployment plan is revised.