It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?
Correct Answer: C
When work is repeatedly "nearly done" but fails iteration expectations and returns to the backlog, the most common control problem is weak adherence to the Definition of Done. The DoD is a shared, explicit quality and completeness standard that ensures increments are potentially shippable and reduces rework. Emphasizing and reinforcing the DoD (C) addresses the systemic cause: inconsistent quality gates, missing testing, incomplete documentation, or unclear completion criteria.