Valid PMI-200 Dumps shared by ExamDiscuss.com for Helping Passing PMI-200 Exam! ExamDiscuss.com now offer the newest PMI-200 exam dumps, the ExamDiscuss.com PMI-200 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-200 dumps with Test Engine here:
What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?
Correct Answer: A
Velocity is a measure of how much work a team completes in a given sprint, typically measured in story points or other units of effort. While velocity can be useful for tracking progress and forecasting future work, it has some limitations when it comes to accurate capacity planning. Velocity can vary from sprint to sprint due to multiple factors, such as the complexity of the tasks, interruptions, or even external influences. This variability can make it difficult to predict how much work a team can handle in future sprints, leading to inaccurate capacity planning.