<< Prev Question Next Question >>

Question 128/195

A project team for a local government is transitioning from a predictive development life cycle to an iterative development life cycle. The project sponsor has informed the team lead that the subject matter expert (SME) for the financial functions of the solution is overallocated, so the team needs to convert the previously gathered requirements into user stories.
What should the agile lead do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (195q)
Question 1: A product owner with experience in a predictive approach wan...
Question 2: (Exhibit) Case Study An agile project lead for a company is ...
Question 3: A large, corporate organization is forced to hire new team m...
Question 4: An agile coach is working on a software development project....
Question 5: During a daily stand up meeting, a developer expresses conce...
Question 6: What should the agile practitioner know about tracking veloc...
Question 7: Halfway through the execution of an agile project, a retrosp...
Question 8: A member of the development team is working on a prioritized...
Question 9: A project team identifies a number of technical challenges w...
Question 10: The project lead of a newly created agile project delivery t...
Question 11: What is the disadvantage of using velocity as a measure of t...
Question 12: A product owner worked with the customer to define the succe...
Question 13: Several potential risks have been identified for a new proje...
Question 14: An agile coach is working with a team that serves clients ma...
Question 15: An agile team is planning the next iteration for a product r...
Question 16: During a project meeting, a team is faced with a difficult d...
Question 17: During an executive review, a scrum master uses a burndown c...
Question 18: If an individual is working on a project team in a phase del...
Question 19: A product owner concludes that the majority of a project's v...
Question 20: An executive sponsor asks a team when a specific feature wil...
Question 21: During backlog refinement, a team routinely creates tests to...
Question 22: A new agile team is forming to address a high-priority proje...
Question 23: The customer needs assistance in determining the efficiency ...
Question 24: While working on a sprint for a software development project...
Question 25: Which agile practice would most significantly increase a tea...
Question 26: Due to its complexity a new team member struggles with devel...
Question 27: An agile team discovers a new risk and identifies that its i...
Question 28: During product development, changes in technology and regula...
Question 29: During a sprint, the team encounters a technical problem tha...
Question 30: What should a Scrum Master do when one team member falls beh...
Question 31: What is a specific development practice that has been effect...
Question 32: When considering impact on a project, to whom should an agil...
Question 33: When working on a new product, what should an agile team do ...
Question 34: The team is aware that they will need to integrate a new com...
Question 35: During a recent sprint review meeting with stakeholders, the...
Question 36: How should the project manager introduce the team, communica...
Question 37: One of the senior stakeholders on a project did not want to ...
Question 38: Part way through a project, several team members are in conf...
Question 39: During sprint retrospectives, some team members are very voc...
Question 40: An infrastructure team had to revamp so downstream channels ...
Question 41: An agile project manager has noticed their teams declining m...
Question 42: The risk profile of a project has increased beyond the upper...
Question 43: Trend analysis shows that velocity is significantly higher t...
Question 44: A scrum master is 6 days into a 10-day iteration. A customer...
Question 45: A project team is currently working on sprint seven of a rel...
Question 46: Stakeholders are displeased with the latest release of a pro...
Question 47: The agile practitioner has determined that two different tea...
Question 48: A client needs to release their product to market earlier th...
Question 49: Conversation transcript between the customer and the product...
Question 50: (Exhibit) An agile development team is working on a digital ...
Question 51: A newly formed scrum team wants to foster an environment of ...
Question 52: The scrum master for a large project must provide an estimat...
Question 53: A project manager is managing a large complex project with c...
Question 54: A Scrum team has worked hard to reach their sprint goal, but...
Question 55: (Exhibit) The product owner is working on an application tha...
Question 56: The productivity of an agile team has fallen significantly i...
Question 57: An agile team wants to collectively determine a project's si...
Question 58: A technical problem arises that will likely impact the stori...
Question 59: A scrum team is working on an important project with a short...
Question 60: A senior manager has asked an agile team to ensure that the ...
Question 61: Early in a project stakeholder analysis is performed: howeve...
Question 62: What do the principles of Extreme Programming (XP) include?...
Question 63: A team is delivering work as per the sprint plan, and team v...
Question 64: In a planning meeting, the client does not have a clear unde...
Question 65: During a Kanban team's daily stand up, an agile coach observ...
Question 66: During a planning session, four out of five team members vot...
Question 67: How should an agile project leader interact with the product...
Question 68: A team member does not understand what the project risks are...
Question 69: An agile team has defined their definition of done (DoD) for...
Question 70: During a retrospective, team members suggest process improve...
Question 71: During a backlog refinement meeting, a senior team member ra...
Question 72: A team is preparing to demonstrate new product capabilities ...
Question 73: Two team members are working together to deliver an asset ma...
Question 74: An organization wants to increase value delivery in its agil...
Question 75: A scrum team is working together virtually. One of the team ...
Question 76: A company has decided to use an agile delivery method for la...
Question 77: After performing three sprints, the product owner and sponso...
Question 78: A new CIO advocates an agile framework for new IT projects, ...
Question 79: One of the overseas stakeholders on an agile project has not...
Question 80: An agile team is preparing a release plan for a project. Wha...
Question 81: A newly formed, colocated team is participating in daily sta...
Question 82: An agile team has been given a complex project with a basic ...
Question 83: The team is refining user stones during the backlog grooming...
Question 84: During project inception, an agile practitioner engages the ...
Question 85: During a team meeting members who are subject matter experts...
Question 86: A stakeholder complains about the amount of changes that are...
Question 87: During sprint planning, team members have differing opinions...
Question 88: A development team and product owner disagree on a user stor...
Question 89: How can the scrum master respond to a stakeholder who sugges...
Question 90: A scrum master is part of a project team using technologies ...
Question 91: Roadmaps are defined as covering a rolling 12 months. When c...
Question 92: A product owner complains that some of the requirements iden...
Question 93: (Exhibit) In a project to develop a supply-and-demand scenar...
Question 94: A scrum master is working with a team on a complex software ...
Question 95: Stakeholders are unhappy because they have not been consulte...
Question 96: Several new stakeholders are concerned about being asked to ...
Question 97: During a coaching session, an agile project manager discusse...
Question 98: The amount of information captured in the project's defects ...
Question 99: An agile team's client has been asked to expedite the delive...
Question 100: A project team has been working on five data source integrat...
Question 101: An agile coach realizes that a team responsible for a major ...
Question 102: An agile practitioner wants to ensure that stakeholders have...
Question 103: An agile project manager is working on a project to develop ...
Question 104: How can an agile project manager ensure that all stakeholder...
Question 105: Management decides to set up a new project to exploit an eme...
Question 106: A new software development team has just been formed. 5 spri...
Question 107: An agile leader has been assigned to a project that involves...
Question 108: During a mature agile team's planning meeting, a team member...
Question 109: A product's scope and acceptance criteria have been defined,...
Question 110: A new stakeholder has recently joined a project. During a me...
Question 111: Several team members have complained to senior management ab...
Question 112: An agile team notices that the same problems continue to occ...
Question 113: Midway through a sprint, the scrum master identifies that re...
Question 114: A development team is calculating the number of story points...
Question 115: The systems integrator for an enterprise resource planning (...
Question 116: An agile team is working on the first sprint, and have alrea...
Question 117: A team member has spent 5 days on a spike and the first set ...
Question 118: The project team is ahead of schedule and beginning lo gold-...
Question 119: Which of the following allows DevOps to enable and sustain a...
Question 120: A high-profile project team is struggling to meet planned ve...
Question 121: As user stories are developed, what should be done to record...
Question 122: A large project team of 20 people from different functional ...
Question 123: A product owner adds user stories to the backlog on a daily ...
Question 124: During the retrospective meeting, it is revealed that an ext...
Question 125: A globally distributed project team is using email and phone...
Question 126: An organization wants to execute a corporate website redesig...
Question 127: A project team has a senior subject matter expert (SME) who ...
Question 128: A project team for a local government is transitioning from ...
Question 129: A customer and a product delivery team meet to discuss a pro...
Question 130: For what is the MoSCoW method used?...
Question 131: An agile team often fails to deliver its sprint goal. At a s...
Question 132: During an iteration planning meeting, the team suggests chan...
Question 133: A team is creating a highly marketed, time-sensitive product...
Question 134: When working with Lean approaches, which process includes th...
Question 135: An agile team member from a cross-functional team has been u...
Question 136: After seeing the planned features (or an upcoming release, a...
Question 137: A team's technical lead believes that manual testing tasks s...
Question 138: A product owner asks a newly formed scrum team how many stor...
Question 139: An executive sponsor of a new scrum team actively attends sc...
Question 140: A client has provided their requirements and deadline to the...
Question 141: On an agile project, some of the development team is struggl...
Question 142: A team retrospective was going well until the team lead intr...
Question 143: A Scrum Master would like to provide information to key stak...
Question 144: The vice president (VP) of an organization has been asked by...
Question 145: A company has decided to combine two similar products consis...
Question 146: During a project's last few sprints, an agile practitioner n...
Question 147: Agile team A struggles to deliver committed stories due to t...
Question 148: During a team meeting, conflicting opinions arise regarding ...
Question 149: A scrum team is experiencing lengthy discussions leading to ...
Question 150: A project sponsor is upset that an enhancement will be unava...
Question 151: A key stakeholder cannot attend the project vision statement...
Question 152: During the iteration planning of a newly onboarded agile tea...
Question 153: The transition of a monthly news publication from paper to d...
Question 154: The agile team disagrees with the business stakeholders on c...
Question 155: How can an agile team working on a new product ensure alignm...
Question 156: What should a team do when they complete all sprint goals ea...
Question 157: A project team developer has been involved in a large corpor...
Question 158: A legal department representative contacts the scrum master ...
Question 159: What is the first thing an agile development team should do ...
Question 160: Toward the end of a project the product owner discovers that...
Question 161: A project manager noticed that a team member had been a cons...
Question 162: An agile project has three more iterations before the releas...
Question 163: An agile project manager is leading an international project...
Question 164: The product owner of a team starts the iteration review with...
Question 165: A new team member asks what changes could accelerate a chang...
Question 166: (Exhibit) A food company seeks additional business-to-busine...
Question 167: New stakeholders are joining a project team where the agile ...
Question 168: An agile team is having a meeting with a customer to formula...
Question 169: After a successful product deployment, a key stakeholder inf...
Question 170: Unable to meet a sprint's committed velocity, an agile team ...
Question 171: During a review session, a customer representative is concer...
Question 172: Senior management is frustrated at the lack of a detailed im...
Question 173: An agile team is struggling to achieve their goal during the...
Question 174: The executive leadership wants to understand ways to better ...
Question 175: A product owner adds a 21-point, high-priority story to a sp...
Question 176: A development team is working on the implementation of a hum...
Question 177: The project lead of a newly created agile project delivery t...
Question 178: During agile training, an aspiring scrum master with experie...
Question 179: An event management team is following an agile approach to p...
Question 180: During the high-level estimation for a project, the team con...
Question 181: Midway through an iteration an agile team learns that a team...
Question 182: A software company is developing an accounting software syst...
Question 183: An executive notices a kanban board in a highly visible loca...
Question 184: (Exhibit) Based on the chart, what is the current status of ...
Question 185: A member of a project's development team approaches the team...
Question 186: An agile practitioner notices that team members are disengag...
Question 187: An agile coach is guiding a team across multiple locations. ...
Question 188: Team A is working on the second sprint of a product release ...
Question 189: An agile team is working on a new product and is behind with...
Question 190: An agile team is having difficulties in obtaining the partic...
Question 191: A team member starts discussing a project roadblock during a...
Question 192: What should a learn consider when calculating the effort nee...
Question 193: A new agile project manager accepts an assignment to manage ...
Question 194: During a review session, an agile team presented done requir...
Question 195: During a project's last iteration, an agile team struggled w...