A project manager is managing a large complex project with cross-functional teams using an adaptive approach. Frequent communication among the team leads of these cross-functional teams is crucial for the project to stay on track and deliver value according to the project plan. Which agile communication practice should the project manager implement to ensure the cross-functional teams interact frequently?
Correct Answer: A
In an adaptive approach to project management, particularly in agile, empowering team leads to manage their teams' issues and impediments is a key practice. This allows for more autonomy within the teams, ensures that obstacles are handled promptly, and promotes frequent communication among team leads. By giving the leads the authority to resolve issues, they can ensure smooth collaboration across cross-functional teams and maintain alignment with the overall project goals.