A project team has been working on five data source integrations. They have allocated one tester for each data source. One of the testers is on emergency leave for personal reasons, so the project deliverables could not be completed on time. How should the project team improve during their retrospective for future implementations?
Correct Answer: B
In this scenario, the team faced delays due to the absence of a single tester. To prevent similar issues in the future, the team should work on becoming more cross-functional, where team members are skilled in multiple areas (e.g., testing multiple data sources). Encouraging team members to become general specialists reduces bottlenecks and dependency on a single individual, ensuring that the team can continue to make progress even if someone is unavailable. This fosters greater flexibility and resilience within the team, improving overall efficiency and minimizing disruptions in future implementations.