A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front. What should the scrum master do?
Correct Answer: C
In agile methodology, particularly in Scrum, it is essential to focus on delivering value through iterative, incremental development. Rather than planning everything upfront for the entire 2-year duration, the focus should be on delivering small, manageable releases on a regular cadence, allowing for flexibility and adaptability based on feedback from stakeholders. This approach helps to ensure that the team remains responsive to changing requirements and can continually improve the product over time.