Conversation transcript between the customer and the product owner (PO): Customer: I am requesting a calendar feature for scheduling and reminding of upcoming releases that we can manage. We also need the calendar to indicate quarterly metrics deadlines, code freeze dates for financial close, and things like that. PO: My understanding is that this is for tracking project deadlines. Would you need to see the project deadlines on your phone calendar? Customer: Yes. I need to see a single snapshot on my phone. So, is it possible for me to connect my phone to this calendar app? PO: Let me write up the requirements and get the development team on board with the deadlines. What phone do you own? Customer: I own an Android phone, but I also need integration with the Apple phones. Identify three minimum viable product (MVP) items. (Refer to Conversation transcript between the customer and the product owner (PO). Choose three.)
Correct Answer: B,E,F
The Minimum Viable Product (MVP) is the smallest set of features needed to satisfy early adopters and deliver value quickly while enabling further development based on feedback. From the conversation: Android phone integration: The customer specifically asks if they can connect their phone to the calendar app, so integrating with Android is a key MVP feature. Scheduler to add events: The customer requests the ability to schedule and manage upcoming releases, including quarterly metrics deadlines and other key dates. This is fundamental functionality for the calendar app. Product increment release dates: The customer wants the calendar to show release dates, so having the ability to display product increment release dates is essential.