How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?
Correct Answer: B
In Scrum, velocity is a metric that measures the amount of work a team can complete in a given sprint, usually measured in story points or work units. However, velocity is not a metric for team efficiency or quality. It primarily reflects the team's capacity to complete work within a sprint and can help forecast future work delivery once the team becomes stable. A team may have a stable velocity, but that does not necessarily mean they are producing higher-quality or more efficient deliverables.