Valid PMI-200 Dumps shared by ExamDiscuss.com for Helping Passing PMI-200 Exam! ExamDiscuss.com now offer the newest PMI-200 exam dumps, the ExamDiscuss.com PMI-200 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PMI-200 dumps with Test Engine here:
A scrum master is 6 days into a 10-day iteration. A customer representative approaches the scrum master and asks whether they can access the latest update on the project. Which action should the scrum master take?
Correct Answer: A
The information radiator is a key tool in Agile that provides a real-time, visual display of the project's current status, including progress, completed tasks, blockers, and upcoming work. This is typically made accessible to all stakeholders and is updated regularly to ensure transparency and communication. Instead of relying on emails or meeting invites, the Scrum Master should direct the customer representative to the information radiator, as it provides the most up-to-date and easily accessible information about the project's progress. This encourages transparency and aligns with Agile principles of open communication and visibility.