You are the business analyst for your organization and your requirements for the endeavor have recently been approved. Your organization creates a baseline for the requirements based on the approval of the requirements. What must happen in your business analysis activities if the requirements for your endeavor need to be changed?
Correct Answer: C
Explanation According to the BABOK® Guide, a change control system is a set of procedures that defines how changes to the approved requirements are initiated, evaluated, authorized, prioritized, planned, implemented, validated, and communicated. A change control system is necessary to manage the impact of changes on the requirements baseline, and to ensure that the changes are aligned with the business need and the solution scope1. References: 1: BABOK® Guide, version 3, section 5.5.1, page 142.