A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system.
The BA aims to define the solution definition before implementation, capture the information in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
Correct Answer: A
Explanation
The predictive approach provides the appropriate level of formality for this project. The predictive approach is a method of planning and managing projects that follows a predefined and sequential process. The predictive approach aims to define the scope, requirements, and deliverables of the project upfront and minimize changes during the implementation. The predictive approach is suitable for projects that have a clear and stable vision, well-understood requirements, and low uncertainty or risk.
The other options are incorrect because:
Option B is incorrect because the reactive approach does not provide the appropriate level of formality for this project. The reactive approach is a method of planning and managing projects that responds to changes and issues as they arise. The reactive approach does not follow a predefined or sequential process, but adapts to the changing needs and expectations of the stakeholders. The reactive approach is suitable for projects that have a vague or evolving vision, unclear or changing requirements, and high uncertainty or risk.
Option C is incorrect because the proactive approach does not provide the appropriate level of formality for this project. The proactive approach is a method of planning and managing projects that anticipates and prevents potential problems or opportunities before they occur. The proactive approach involves identifying, analyzing, and mitigating risks, as well as enhancing benefits and value. The proactive approach is suitable for projects that have a complex or dynamic environment, multiple or conflicting stakeholder interests, and significant impacts or dependencies.
Option D is incorrect because the adaptive approach does not provide the appropriate level of formality for this project. The adaptive approach is a method of planning and managing projects that delivers the solution in increments or iterations. The adaptive approach involves frequent feedback, collaboration, and testing to ensure that the solution meets the stakeholder needs and expectations. The adaptive approach is suitable for projects that have an emergent or innovative vision, flexible or variable requirements, and moderate uncertainty or risk.
References:
BABOK Guide v3, section 3.2: Plan Business Analysis Approach
CCBA Exam Questions, question 21