The following chart represents attendance of subject matter experts (SME) and the solution owner for a requirements review and approval meeting held weekly by a business analyst (BA).

The requirements package was approved by the solution owner during the May 30 meeting. After implementation of the solution, the BA learns that the users in SME-3 s area are not using the system. Which business analysis activity should the BA have monitored more closely to mitigate this situation?
Correct Answer: D
Explanation
The BA should have monitored stakeholder engagement more closely to mitigate this situation. This is because stakeholder engagement is the process of ensuring that stakeholders are involved in the business analysis activities and that their needs and expectations are met. The chart shows that SME-3 did not attend any of the requirements review and approval meetings, which means that they were not engaged in the project and did not provide their feedback or approval on the requirements. This could lead to resistance or dissatisfaction with the solution. The BA should have identified and communicated with SME-3 and other key stakeholders throughout the project to ensure their buy-in and support. References:
BABOK Guide, section 2.4: Manage Stakeholder Collaboration
CCBA Practice Test, question 99