A business analyst (BA) has completed multiple workshops involving a number of stakeholders including the project manager however, the elicitation results are inconsistent between the stakeholders. How should the variation in results be resolved?
Correct Answer: D
Explanation The BA should model the elicited requirements in a review meeting to resolve the variation in results among stakeholders after completing multiple workshops involving them. Modeling the elicited requirements means creating graphical or textual representations of the requirements to communicate their meaning, structure, relationships, or behavior. Modeling the elicited requirements in a review meeting can help to resolve any inconsistencies, conflicts, gaps, or ambiguities among stakeholder perspectives. The other options are incorrect because: Option A is incorrect because letting the project manager decide which requirement is relevant is not a way to resolve the variation in results among stakeholders after completing multiple workshops involving them. This is an authoritative technique that is based on the power or influence of a single person or group over others. Authoritative techniques can expedite or simplify the decision-making process, but they may not reflect the consensus or agreement of all stakeholders. Option B is incorrect because letting the BA select which requirements are correct is not a way to resolve the variation in results among stakeholders after completing multiple workshops involving them. This is an authoritative technique that is based on the power or influence of a single person or group over others. Authoritative techniques can expedite or simplify the decision-making process, but they may not reflect the consensus or agreement of all stakeholders. Option C is incorrect because letting the project manager model requirements in a review meeting is not a way to resolve the variation in results among stakeholders after completing multiple workshops involving them. This is an authoritative technique that is based on the power or influence of a single person or group over others. Authoritative techniques can expedite or simplify the decision-making process, but they may not reflect the consensus or agreement of all stakeholders. References: BABOK Guide v3, section 10.30: Data Modeling CCBA Exam Questions, question 23