Valid CFM Dumps shared by ExamDiscuss.com for Helping Passing CFM Exam! ExamDiscuss.com now offer the newest CFM exam dumps, the ExamDiscuss.com CFM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CFM dumps with Test Engine here:
When a facility manager initiates an office relocation project, which item is completed first?
Correct Answer: C
Theproject charteris thefirst stepin initiating any office relocation project. It serves as theformal authorizationthat outlines: * Project scope- Defines what is included/excluded. * Objectives- Establishes the purpose and expected outcomes. * Key stakeholders- Identifies project sponsors, decision-makers, and involved teams. * Preliminary timeline and budget- Provides a high-level cost estimate and schedule. Without aproject charter, there is noofficial approval or frameworkfor developing theprogram, securing budgets, or signing new leases.