When a facility manager initiates an office relocation project, which item is completed first?
Correct Answer: C
Theproject charteris thefirst stepin initiating any office relocation project. It serves as theformal authorizationthat outlines: * Project scope- Defines what is included/excluded. * Objectives- Establishes the purpose and expected outcomes. * Key stakeholders- Identifies project sponsors, decision-makers, and involved teams. * Preliminary timeline and budget- Provides a high-level cost estimate and schedule. Without aproject charter, there is noofficial approval or frameworkfor developing theprogram, securing budgets, or signing new leases.