Valid CFM Dumps shared by ExamDiscuss.com for Helping Passing CFM Exam! ExamDiscuss.com now offer the newest CFM exam dumps, the ExamDiscuss.com CFM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CFM dumps with Test Engine here:
The building automation systems (BAS) experienced a power loss. The systems are now back online and are accessible by remote monitoring controls. From a remote login, you observe that the indoor air temperatures are warmer than the settings. What should you do?
Correct Answer: C
When aBuilding Automation System (BAS)comes back online after a power loss,physical verification of HVAC equipment operation is essentialto: * Confirm system restart success- Some components may not fully reboot. * Check for mechanical failures- Power loss could trigger equipment malfunctions. * Avoid incorrect system readings- Remote monitoring may not reflect actual conditions. Lowering temperature settings (Option A) isineffectivebecause it will not speed up cooling. Calling an onsite occupant (Option B) provideslimited insightinto the system's condition. While installing agenerator (Option D)is along-term solution, it does notaddress the immediate issue.