As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?
Correct Answer: D
The correct answer is D - Periodically, at both the release and project level. Agile planning is iterative and layered. When new requirements or constraints emerge, plans should be updated at the appropriate levels-sprint, release, and potentially the overall project level. Periodic adjustments ensure continued alignment with business needs and system dependencies. PMI Agile Practice Guide: "Agile planning is done at multiple levels: product vision, roadmap, release, iteration, and daily. These plans are continually updated based on new learning and stakeholder feedback." (PMI Agile Practice Guide, Section 5.3 - Adaptive Planning) Mike Griffiths: "Effective planning includes periodic updates at all planning horizons. Adjusting at both the project and release levels ensures strategic alignment and tactical feasibility." (PMI-ACP Exam Prep, Chapter 5 - Adaptive Planning) Incorrect options: * A misses the iterative nature of Agile planning. * B and C are too narrow in scope.