A team worked with a customer to estimate all user stories for the must have features. During release planning sessions, the customer indicated they prefer 3-week iterations that begin on Thursdays and end on Wednesdays. The team spent several days determining which stories should be developed for iteration 0 and understanding the customer's priorities for the remaining stories. The project sponsor attends the Friday meeting and requests a high-level estimate of when they can invite the chief executive officer (CEO) to a demonstration of the minimum viable product (MVP). What should the team tell the sponsor at this point in the planning process?
Correct Answer: C
At this point in the planning process, the team has not yet gathered enough data to provide a precise release date. The team's velocity (the amount of work they can complete in each iteration) has not been established, and the team needs some iterations to stabilize and gather insights. However, they can offer a broad range based on the current understanding of the backlog and priorities. This allows the sponsor to have a rough expectation while also managing the uncertainty involved at this stage in the process.