A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently. What is the estimated time remaining for the project?
Correct Answer: C
Understand the current progress: The project is halfway through development. The team has reached a stable velocity after 8 iterations. Each sprint duration is two weeks. Determine the remaining number of iterations: Since the project is halfway completed, an equal amount of work remains. If 8 iterations have been completed, 8 more iterations are required to complete the project. Calculate the remaining time: Each iteration (sprint) lasts 2 weeks. 8 iterations × 2 weeks per iteration = 16 weeks. * 16 weeks = 4 months.