A development team is working on the implementation of a human resources (HR) solution. The team has decided to work together with different business units to deliver value early and often. Which agile values are being practiced in this scenario?
Correct Answer: B
In this scenario, the development team is working closely with different business units to deliver value early and often. This aligns with the agile value of delivering working software frequently, with a preference for shorter timescales. By collaborating with business units, the team is enabling early feedback and adapting to changing requirements, which is a core principle of agile methodologies like Scrum.