Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Correct Answer: D
Explanation/Reference: Explanation: 9.2.2.1 Pre-assignment When project team members are selected in advance, they are considered pre-assigned. This situation can occur if the project is the result of specific people being identified as part of a competitive proposal, if the project is dependent upon the expertise of particular persons, or if some staff assignments are defined within the project charter.