Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Correct Answer: A
Explanation/Reference: Explanation: Process: 10.1 Plan Communications Management Definition: The process of developing an appropriate approach and plan for project communications based on stakeholder's information needs and requirements, and available organizational assets. Key Benefit: The key benefit of this process is that it identifies and documents the approach to communicate most effectively and efficiently with stakeholders. Inputs 1. Project management plan 2. Stakeholder register 3. Enterprise environmental factors 4. Organizational process assets Tools & Techniques 1. Communication requirements analysis 2. Communication technology 3. Communication models 4. Communication methods 5. Meetings Outputs 1. Communications management plan 2. Project documents updates