A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Correct Answer: C
Explanation/Reference: A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity. For example, a technical writing team may begin editing the draft of a large document 15 days after they begin writing it. Process: 6.3 Sequence Activities Definition: The process of identifying and documenting relationships among the project activities. Key Benefit: The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints. Inputs 1. Schedule management plan 2. Activity list 3. Activity attributes 4. Milestone list 5. Project scope statement 6. Enterprise environmental factors 7. Organizational process assets Tools & Techniques 1. Precedence diagramming method (PDM) 2. Dependency determination 3. Leads and lags Outputs 1. Project schedule network diagrams 2. Project documents updates