What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Correct Answer: C
Explanation/Reference: Explanation: Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance. EAC 'atypical' = AC + BAC - EV EAC 'typical' = AC + ((BAC - EV) / CPI)