Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
When can pre-assignment of project team members occur?
Correct Answer: D
Explanation/Reference: Explanation: 9.2.2.1 Pre-assignment When project team members are selected in advance, they are considered pre-assigned. This situation can occur if the project is the result of specific people being identified as part of a competitive proposal, if the project is dependent upon the expertise of particular persons, or if some staff assignments are defined within the project charter.