11.6.2.5 Reserve Analysis
Throughout execution of the project, some risks may occur with positive or negative impacts on budget or schedule contingency reserves. Reserve analysis compares the amount of the contingency reserves remaining to the amount of risk remaining at any time in the project in order to determine if the remaining reserve is adequate.
Process: 11.6 Control Risks
Definition: The process of implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project.
Key Benefit: The key benefit of this process is that it improves efficiency of the risk approach throughout the project life cycle to continuously optimize risk responses.
Inputs
1. Project management plan
2. Risk register
3. Work performance data
4. Work performance reports
Tools & Techniques
1. Risk reassessment
2. Risk audits
3. Variance and trend analysis
4. Technical performance measurement
5. Reserve analysis
6. Meetings
Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates
6.5.2.6 Reserve Analysis
Duration estimates may include contingency reserves, sometimes referred to as time reserves or buffers, into the project schedule to account for schedule uncertainty. Contingency reserves are the estimated duration within the schedule baseline, which is allocated for identified risks that are accepted and for which contingent or mitigation responses are developed. Contingency reserves are associated with the "known- unknowns," which may be estimated to account for this unknown amount of rework.
As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Contingency should be clearly identified in schedule documentation.
[..]
Estimates may also be produced for the amount of management reserve of time for the project.
Management reserves are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Management reserves are intended to address the "unknown-unknowns" that can affect a project. Management reserve is not included in the schedule baseline, but it is part of the overall project duration requirements. Depending on contract terms, use of management reserves may require a change to the schedule baseline.