A project manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?
Correct Answer: A
Explanation/Reference: Explanation: T&M contracts are often used for staff augmentation, acquisition of experts and any outside support when a precise statement of work is not quickly prescribed.