Valid CAPM Dumps shared by ExamDiscuss.com for Helping Passing CAPM Exam! ExamDiscuss.com now offer the newest CAPM exam dumps, the ExamDiscuss.com CAPM exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CAPM dumps with Test Engine here:
Which of the following is an input into the Develop Project Team process?
Correct Answer: C
Explanation/Reference: Explanation: 9.3 Develop Project Team Definition: The process of improving competencies, team member interaction, and overall team environment to enhance project performance. Key Benefit: The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance. Inputs 1. Human resource management plan 2. Project staff assignments 3. Resource calendars Tools & Techniques 1. Interpersonal skills 2. Training 3. Team-building activities 4. Ground rules 5. Colocation 6. Recognition and rewards 7. Personnel assessment tools Outputs 1. Team performance assessments 2. Enterprise environmental factors updates