Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
Correct Answer: D
Explanation/Reference: Explanation: Process: 4.1. Develop Project Charter Definition: The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. Key Benefit: The key benefit of this process is a well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project. Inputs 1. Project statement of work 2. Business case 3. Agreements 4. Enterprise environmental factors 5. Organizational process assets Tools & Techniques 1. Expert judgment 2. Facilitation techniques Outputs 1. Project charter