The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders. What should the business analyst do?
Correct Answer: A
A change control process is a set of procedures that defines how changes to the requirements are identified, assessed, approved, implemented, and communicated. A change control process helps to ensure that changes are aligned with the business objectives, do not introduce unnecessary risks, and do not adversely affect the quality of the solution. A change control process also helps to manage stakeholder expectations and avoid scope creep. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 13; Business Analysis for Practitioners: A Practice Guide2, page 77.