In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope. What task should the business analyst perform in order to identify these impacts?
Correct Answer: A
Managing solution scope is the task of ensuring that the solution meets the agreed-upon requirements and delivers the expected value to the stakeholders. Managing solution scope involves analyzing the impact of any changes to the scope, assessing the feasibility and risks of the changes, and obtaining approval from the stakeholders before implementing the changes. Managing solution scope can help the business analyst to identify the impacts, dependencies, or risks associated with the addition to the scope. References: = PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline (2019), page 14; Business Analysis for Practitioners: A Practice Guide (2015), page 83.