A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.
Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
Correct Answer: B
A configuration management system is a tool that can be used to trace the large number of requirements that will be generated by this project. A configuration management system is a system that consists of the processes, procedures, tools, and databases that are used to manage and control the configuration items of the project. A configuration item is any component of the project that has a defined and approved version, such as a requirement, a deliverable, a document, a model, a test case, etc. A configuration management system can help the business analyst and the project team to record, track, update, and maintain the configuration items throughout the project lifecycle, and to ensure their consistency, integrity, and traceability. A configuration management system can also help to handle changes, resolve issues, and measure the quality and performance of the project. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 24; Business Analysis for Practitioners: A Practice Guide2, page 133.