A project was in the design phase when the team received news of a new regulatory mandate that affects the project. The requirements have already been approved and baselined. If the new requirements are not included, the company will be out of compliance and may face monetary penalties. What should the business analyst do next?
Correct Answer: C
The business analyst should follow the change control process to handle the new regulatory mandate that affects the project. The change control process is a set of procedures that defines how changes to the requirements or the project scope are identified, analyzed, approved, and implemented. The change control process helps to ensure that changes are aligned with the business need, the project objectives, and the stakeholder expectations. References: PMI Guide to Business Analysis, Chapter 9, Section 9.4.1; PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline, Domain IV: Traceability and Monitoring, Task 2.