A project that was going well for the last few months has encountered a situation-regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected. This could have been avoided if:
Correct Answer: B
This situation could have been avoided if a change control process for requirements and their statuses was followed. A change control process is a set of procedures and tools that helps the business analyst to manage changes to the requirements, and to document and communicate the impact and approval of the changes. A change control process also helps to maintain the traceability and quality of the requirements, and to ensure that they are aligned with the business needs and the project scope. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 23; Business Analysis for Practitioners: A Practice Guide2, page 131.