An enterprise's internal audit group has scheduled a control review of a payroll system project but has been told to wait until the system is implemented. Which of the following is the GREATEST risk associated with the delay?
Correct Answer: C
Delaying the control review of a payroll system project until after its implementation increases the risk of discovering control weaknesses or errors that could have been prevented or corrected earlier. This would result in increased cost to mitigate the deficiencies and ensure the system's reliability and compliance. References: CGEIT Domain 4: Risk Optimization