Who is responsible for tracking the remaining work of the Sprint?
Correct Answer: A
According to the Scrum Guide1, only people who are actively working on items in the Sprint Backlog participate in updating it during a Sprint; this includes tracking progress made on those items. This is typically done by Developers updating their remaining work every day after their Daily Scrum. The Development Team tracks this total work remaining at least for every Daily Scrum to project the likelihood of achieving their Sprint Goal.