When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Correct Answer: C
When a Development Team determines that it will not be able to finish the complete forecast, both the Product Owner and the Development Team have to be present when reviewing and adjusting the Sprint work selected, as stated in [6]: "If there is not enough work remaining for all members of a Development Team then they can renegotiate scope with their Product Owner. If there is too much work remaining then they can also renegotiate scope with their Product Owner."