Who determines how work is performed during the Sprint?
Correct Answer: B
The correct answer is B, because the Development Team determines how work is performed during the Sprint. The Scrum Guide states that "development Teams are self-organizing. No one (not even the Scrum Master) tells the Development Team how to turn Product Backlog into Increments of potentially releasable functionality." Therefore, the Development Team has the autonomy and responsibility to organize and manage its own work.