What happens if the Development Team cannot complete its work by the end of the Sprint?
Correct Answer: B
If the Development Team cannot complete its work by the end of the Sprint, then the Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length, as stated in [7]: "If a Development Team determines it has overcommitted itself for a Sprint, one option is to collaborate with the Product Owner to negotiate removing or reducing scope. Another option is to simply work hard and do its best, without cutting quality or pressuring individuals. In either case, the Development Team learns from its experience and uses this learning when planning future Sprints."