A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
Correct Answer: A,B
The Product Owner is responsible for ensuring that the most valuable functionality is produced first, at all times, by ordering and prioritizing the Product Backlog. The Product Owner also interacts with stakeholders to understand their needs and expectations, and to communicate the vision and progress of the product. The other options are not part of the Product Owner role according to Scrum, as they are either too prescriptive or too technical.