If burndown charts are used to visualize progress, what do they track?
Correct Answer: C
The correct answer is C, because if burndown charts are used to visualize progress, they track work remaining across time. A burndown chart is a graphical representation of the amount of work left to do versus the time available. It helps the Scrum Team monitor and forecast the progress toward the Sprint Goal.