The correct answer is E, because any of the above (or others) which are a decomposition of the selected Product Backlog items can be included in the Sprint Backlog. The Scrum Guide states that "the Sprint Backlog is the set of Product Backlog items selected for the Sprint, plus a plan for delivering the product Increment and realizing the Sprint Goal." Therefore, any work items that help the Development Team achieve the Sprint Goal can be part of the Sprint Backlog.